Inverter substation for an industrial solar plant: 10 kV switchgear, transformer and inverter hall in one block
Four КТП-1000/10/0.4 У1 containerised inverter substations for a solar plant: 4000 kVA and 3.2 MW of inverter capacity in total. Switchgear, transformer and an 8-inverter hall in each block. Odesa, 2021.
A containerised inverter substation for a solar power plant: one enclosure holding 10 kV switchgear, a 1000 kVA power transformer and a compartment for 8 inverters of 100 kW each. Insulated body with air conditioning, fire detection and its own lighting. Four such substations built at our own plant in Odesa — 4000 kVA and 3.2 MW of inverter capacity in total.
The task
The solar plant needed a substation that combines three functionally different zones in a single unit:
- the inverter hall — equipment that generates heat, needs cooling and regular access;
- the power transformer — oil-filled, with its own containment requirements;
- the 10 kV switchgear — a high-voltage zone with restricted access.
You cannot simply place these three side by side: they have different climate, access and fire-safety requirements. On top of that came a commercial condition — a certificate of origin (form U-1), without which the plant would not qualify for its feed-in tariff premium.
The solution
We used a segregated layout within one block: 10 kV switchgear, transformer compartment and inverter hall as separate zones, each with its own doors and its own conditions.
Inverter hall.
Per the passport, each substation holds 8 inverters of 100 kW. Built into the structure:
- embedded fixings for the inverter mounting frames, dimensioned for their weight;
- PV cable entry through a dedicated floor opening beneath each inverter, plus a spare; then along the walls in galvanised trays;
- circuit-breaker extension bars for cables of 95–240 mm²;
- dedicated earthing points for the inverters — 35 mm² copper — and from 6 mm² for the trays.
Climate and safety. Air conditioning with at least 8 kW of cooling capacity, working and emergency lighting, fire detection, and an auxiliary supply board. The roof is insulated with at least 100 mm of non-combustible material — supplied with its non-combustibility certificate.
Transformer compartment. Oil containment sump and collector sized to hold the required oil volume per the electrical installation code — shown on the frame drawing.
10 kV switchgear. Cells rated IP54, with sealable cable entries and exits. The working current was taken with a 20% margin. The 10 kV busbars are aluminium; internal wiring is copper.
Telecontrol readiness. The protection scheme includes a telecontrol terminal block with breaker position contacts and provision for remote-control contacts on the vacuum circuit breaker. Space is also allowed for a class A power quality analyser with telemetry readout, coordinated with the telecontrol contractor and the DSO's requirements.
Installation documentation. Delivered with the unit: the frame structure in DWG (so the client could design the foundation), a dimensional drawing with the inverter layout, protection schematics and specifications.
The series product card: concrete packaged transformer substation (БКТП). For designers: the typical solutions "1000 kVA substation for solar plants" and "package substation for solar plants". We also build the plants themselves: turnkey industrial solar plants.
Figures (from the passports)
КТП-1000/10/0.4 У1 packaged inverter transformer substation
Serial Nos. 172936, 172937, 172938, 172939 · passport Э-21-311 ПС · Odesa, 2021
| Substations built | 4 |
| Rating of each substation | 1000 kVA |
| Rated voltage, HV side | 10 (6) kV |
| Rated voltage, LV side | 0.4 kV |
| Rated frequency | 50 and 60 Hz |
| Thermal withstand current (1 s), HV side | 25 kA |
| Thermal withstand current (1 s), LV side | 20 kA |
| Electrodynamic withstand current, HV side | 63 kA |
| Electrodynamic withstand current, LV side | 51 kA |
| Insulation level | normal (GOST 1516.1) |
| Climatic design | У1 (GOST 15150), up to 1000 m altitude |
| Transformer LV neutral | solidly earthed |
| Technical spec | TU U 31.2-31681625.001-2003 |
Bill of supply per substation (from section 4 of the passport)
| КСО-Е cells (variants 17, 11, 00*) — 10 kV, 630 A | 3 |
| ЩО 90-1116 panel — 0.4 kV, 2000 A | 1 |
| ЩО 90-1431 panels — 0.4 kV, 1000 A | 2 |
| Auxiliary supply board (ЩВП) — 0.4 kV, 16 A | 1 |
| ТМГ-1000/10/0.4-D/Yн-11 power transformer — 1000 kVA | 1 |
| Inverters — 0.4 kV, 100 kW each | 8 |
| Data logger | 1 |
| Fire detection unit | 1 |
| Fans | 7 |
🔢 Order totals: 4 substations × 1000 kVA = 4000 kVA; 4 × 8 = 32 inverters of 100 kW, i.e. 3.2 MW of inverter capacity. Plus 12 КСО-Е cells and 12 ЩО-90 panels — all of our own manufacture.
From the order requirements (parameters the passport does not cover): cell ingress protection IP54 · +20% working current margin · roof insulation at least 100 mm of certified non-combustible material · air conditioning with at least 8 kW cooling capacity · oil sump and collector per the installation code · aluminium 10 kV busbars, copper internal wiring · PV cables 95–240 mm² · earthing 35 mm² for inverters, from 6 mm² for trays · RAL 7040 finish · service life at least 25 years, warranty at least 24 months · certificate of origin form U-1 (for the feed-in tariff premium).
Why this is harder than a standard package substation
A standard transformer substation has two zones: high voltage and low voltage. Here there are three, and the third one plays by different rules: inverters generate heat, so they need cooling; they are serviced more often, so access has to be convenient; a dozen large-section power cables run to them, so entries are designed per device. Packing all of that into one transportable block is a separate engineering job — and it is solved at the design stage, not during installation.
One more thing the passport shows. Inside the substation sits our own equipment: three 10 kV КСО-Е cells and three 0.4 kV ЩО-90 panels (one at 2000 A and two at 1000 A), plus the auxiliary supply board. The station is not assembled from other people's subsystems — it is built from products of the same plant, from the 10 kV cell to the 0.4 kV panel and the enclosure itself.
Photo report: finished blocks before shipment

We'll cost an inverter substation for your solar plant
Send us the number and model of inverters, the transformer rating and your DSO's requirements — we'll build the block with switchgear, transformer compartment and inverter hall, complete with climate control, fire detection and telecontrol readiness.
Need a similar project?
We’ll estimate yours
Send us your specification or describe the task — we will propose a solution and estimate the time and cost. Preliminary reply within 24 hours.
+380 67 104 94 91