Home/Projects/A four-transformer packaged substation: a distribution point in a modular building

A four-transformer packaged substation: a distribution point in a modular building

A healthcare site needed a supply that does not depend on any single point. We built a packaged switchgear assembly in a modular building: 6 kV switchgear plus **four transformer bays**, grouped into two independent sets. The building arrived on site complete. ---

A four-transformer packaged substation: a distribution point in a modular building

The task

A hospital has no "unimportant" circuits. Operating theatres, intensive care, oxygen plant, refrigerators holding medicines, lifts — these are loads for which an interruption is measured in consequences rather than inconvenience. The supply scheme for such a site is therefore built on redundancy: not one transformer but several, and not one section but several independent ones.

The second part of the task was the site itself. Building a permanent substation on the grounds of a working institution means closing an access road, bringing in plant and stretching the work over months while the institution carries on operating. This is not a place where a construction site can sit for long.

The third was maintenance. Four transformers in one building generate heat. The distribution point needs bays with forced ventilation, and a layout in which staff can reach any cubicle without entering someone else's bay.

The solution

We built a packaged switchgear assembly in a modular building — a product manufactured and fitted out at the plant that arrives on site complete.

  • Four transformer bays in two sets. The division is visible on the facade: two bays belong to one substation and two to the other, and within each pair the transformers are labelled "Tr-r 1" and "Tr-r 2". So this is not "four transformers in a row" but two independent two-transformer substations under one roof. The loss of one does not leave the site without supply.
  • Each transformer in its own bay with its own doors. Reaching one transformer does not mean opening the neighbouring bays: the bays are separated and the double doors run the full width, so a transformer can be rolled out without dismantling the building.
  • Forced ventilation. Every transformer bay door carries a louvre and an axial fan. This is not natural extraction and hope: four transformers under one roof in summer heat need controlled heat removal, otherwise the load has to be curtailed.
  • A separate 6 kV switchgear bay. The medium-voltage switchgear sits in its own section of the building with its own entrance — 6 kV switching and the transformers do not overlap in access or in maintenance.
  • An internal service corridor. The cubicles stand in two rows along a walkway: staff work from the fronts while standing in the corridor rather than squeezing between equipment. Lighting and cable routes run along the ceiling, and the floor sits above a cable trench.
  • A finished building delivered to site. The module was set on a prepared base with paving on either side and the access road kept clear. Installation comes down to placing and connecting rather than building: for a working hospital that means days of work instead of months.
  • A pitched roof with an overhang all round, so water is thrown clear of the wall panels rather than running down the doors and louvres.

Why a packaged building rather than a permanent one. A modular distribution point is assembled and tested in a workshop that has a crane, a test bay and inspection, rather than on an open site. What arrives is a factory-built product — and the time normally spent on construction goes into connection instead.

Figures (from the passports)

🔴 This case deliberately carries no technical data table. No factory passports of the order's own were found in the documents for order 388 (explained in the internal section). I did not put in ratings by guesswork or from another job's paperwork: everything above is read off the photographs of the site — the construction, the number of bays, the layout of the building, the ventilation.

When the passports turn up, the table gets added as a single block.

The series product card: Packaged switchgear assemblies in modular buildings. For design engineers: the standard solution Typical solution: a four-transformer packaged building. A related case: Substations, package substations and distribution points — completed sites.

Photo report from production

The modular switchgear building on its prepared base at the site The complete building: 6 kV switchgear section and transformer bays under one roof End elevation with the pitched roof and its overhang The packaged switchgear building seen from the corner Transformer bays with louvres and forced ventilation Service corridor inside the building: cubicles in two rows Row of cubicles along the walkway, cable routes along the ceiling Control panel and apparatus inside the distribution point A transformer in its own bay: fans on opposite walls, rails for withdrawal

We will build to your diagram

Do you need a distribution point with several transformers for a site that is already in operation? Send us a single-line diagram and our engineer will price the building layout, the cubicle schedule and the lead time. Preliminary quotation within 24 working hours.

Need a similar project?
We’ll estimate yours

Send us your specification or describe the task — we will propose a solution and estimate the time and cost. Preliminary reply within 24 hours.

+380 67 104 94 91
Discuss the project

Send your single-line diagram or specification to info@lk-energy.com.ua — or we will contact you and ask.

+380 67 104 94 91you can copy the numberLeave your number — we’ll call back →
+38 067 104-94-91